The plant is inspected and the technical execution is compared to the requirements of the design documents. Compliance with any restrictions expressed in the Certification Report is assessed as far as possible. Selected tests from the commissioning manual are carried out with a focus on the safety tests. In addition, the practicability of the tests is verified and the turbine behaviour is assessed for compliance with the design documents.
During surveillance of commissioning the following items are examined:
- General appearance
- Conformity of the main components with the certified design documentation and traceability / numeration of the same
- Operating tests and tests of the safety system
- Corrosion protection
- Damages
After witnessing of commissioning a Certification Report is issued.